Make a task depend on another task

When one task cannot be done unless another task is done first, set up a dependency to track the relationship between the two tasks.

  1. In the CollabNet Sites view, expand a task and select either of the these nodes:
    • Right-click Predecessors to specify tasks that must be completed before this task can be done, and choose Create dependency.
    • Select Successors to specify tasks that can be completed only after this task is done, and choose Create dependency.
  2. In the Create Dependency window, enter the ID or browse to the tasks(s) you're relating.
  3. Enter a comment that describes the relationship and click OK.
Tip: In the CollabNet Sites view, you can also create dependencies by dragging a task onto another task.
To delete a dependency, right-click a predecessor or successor task and select Remove dependency.